The film “Skandia Gateway” shows how it will soon be possible for the world’s largest ship to enter the Port of Gothenburg fully loaded and provide increased efficiency and less climate footprint.

The fairway needs to be deepened to 17.5m if the world’s largest ocean-going vessels are to be able to call at the Port of Gothenburg fully loaded. This will prove crucial if Swedish industry is to have greater access to the world in the future. The Skandia Gateway project is already underway and construction is scheduled to begin during the first quarter of next year.

“We are keeping to the timetable and looking forward to breaking ground. At the moment we are working with technical solutions, calculations, risk analyses, and other preconstruction work. The environmental permit process is taking place in parallel at the Land and Environment Court. We hope to secure an environmental permit in time for commencement of construction at the beginning of next year,” said Jan Andersson, Skandia Gateway Project Manager at the Gothenburg Port Authority.

The permit application was submitted to the Land and Environment Court just before Christmas 2020, and during the spring additional documentation will be provided as necessary.

“Everything is proceeding according to plan and no unexpected opinions or objections have emerged. We are looking forward with confidence to seeing how the process will unfold as we move on to the main hearing,” said Kristina Bernstén, Skandia Gateway Sub-Project Manager, Environment, at the Gothenburg Port Authority.

Skandia Gateway has three funding bodies: the Swedish Transport Administration, the Swedish Maritime Administration, and the Gothenburg Port Authority. The port is responsible for the cost of reinforcing the quays and dredging the docks.

“We aim to build sustainably, which means that financial and environmental considerations are our first priority. We are choosing the construction materials carefully and we are conscious of the fact that the quays need to be fit for purpose for many generations to come. To ensure this, the focus in our technical solutions is firmly on life-cycle cost analyses with a 100-year horizon. A higher investment cost initially will be outweighed by lower maintenance costs over time,” said Jan Andersson.

A film has been made to show the need and the importance of having a deeper port area if Swedish industry is to develop in the future. The film explains the work behind increasing the depth of the docks and the fairway from the current 13.5m to 17.5m. Dredging 6km of fairway will result in the removal of 12 million cubic metres of clay. At Skandiahamnen, the existing terminal and 1.2km of quays will be reinforced to allow two ocean-going vessels to load and discharge at the same time.

The first phase in the construction of Skandia Gateway is scheduled for completion in 2026.

Click here to watch the film

The post Construction of Skandia Gateway on track appeared first on Logistics Business® Magazine.



Packers and movers in peenya Packers and movers in peenya Packers and movers near me Packers and movers near me Packers And Movers Banashankari Bangalore a Packers And Movers Banashankari Bangalore a Packers And Movers Jayanagar Packers And Movers Jayanagar Packers and movers Yelahanka Packers and movers Yelahanka Packers And Movers Btm Layout Packers And Movers Btm Layout Packers And Movers Koramangala Packers And Movers Koramangala Packers And Movers Hsr Layout Packers And Movers Hsr Layout Packers And Movers Bommanahalli Packers And Movers Bommanahalli Packers And Movers Begur Road Packers And Movers Begur Road Local Packers And Movers Bangalore Local Packers And Movers Bangalore Packers And Movers Ramamurthy Nagar Packers And Movers Ramamurthy Nagar Packers and movers Bangalore Packers and movers Bangalore